Filters
Question type

Study Flashcards

Three processes are involved in the manufacturing of Chemical Z.First,the raw mixture goes through the Mixing Process,then the Heating Process,and finally the Bottling Process.The hourly production capacity of the three processes is 400 units,600 units and 400 units respectively.Assume that a recent process improvement has resulted in a 20 per cent increase in the capacity of the Bottling Process.This process improvement will:


A) Increase the production of Chemical Z by 80 units per hour
B) Increase the production of Chemical Z by 120 units per hour
C) Increase the production of Chemical Z by 200 units
D) Have no effect on the production level per hour

E) B) and C)
F) All of the above

Correct Answer

verifed

verified

Which of the following is not a characteristic of total quality management?


A) A focus primarily on internal customers
B) All members of the organisation are responsible for quality measures
C) Statistical process control
D) Continuous improvement measures

E) A) and C)
F) A) and B)

Correct Answer

verifed

verified

Internal failure costs refer to costs incurred:


A) in determining whether defects exist
B) because defective products or services are delivered to customers
C) in determining customer demand
D) when defective products or services are detected before leaving the business

E) None of the above
F) All of the above

Correct Answer

verifed

verified

Which of the following time drivers contribute to non-value-added activities? i.Poor quality ii.Efficient inventory management iii.Bottlenecks in production iv.Poorly structured delivery processes


A) i,ii and iii
B) i,iii and iv
C) i,ii and iv
D) All of the given answers

E) All of the above
F) None of the above

Correct Answer

verifed

verified

Consider a situation where an activity-based costing system is in use rather than a conventional volume-based costing system.Which of the following statements is/are true?


A) The use of activity-based costing eliminates the need to consider qualitative factors.
B) When an activity-based costing system is used,facility level costs will have to be analysed differently to the way they would be under a traditional volume-based costing system.
C) When an activity-based costing system is used,unit level costs will have to be analysed differently to the way they would be under a traditional volume-based costing system.
D) None of the given answers.

E) A) and C)
F) C) and D)

Correct Answer

verifed

verified

The following are the expected quality costs for a firm for a selected period.Calculate the amount of external failure costs. The following are the expected quality costs for a firm for a selected period.Calculate the amount of external failure costs.   A)  $33 000 B)  $37 500 C)  $42 000 D)  $37 000


A) $33 000
B) $37 500
C) $42 000
D) $37 000

E) B) and D)
F) B) and C)

Correct Answer

verifed

verified

D

Assuming one answer only can be chosen,which of the following is a non-value-added activity for a manufacturing firm?


A) Machining a metal plate in the factory.
B) Packing finished product into cartons for delivery.
C) Moving partly finished production to storage.
D) Inserting a warranty-card and instruction booklet into the boxed product.

E) B) and D)
F) None of the above

Correct Answer

verifed

verified

Cost drivers and a process perspective,are two of the main differences between contemporary and conventional approaches to cost management.

A) True
B) False

Correct Answer

verifed

verified

If the target selling price is $120 and the target profit margin is a 40 per cent mark-up on cost,what is the target cost?


A) $48
B) $72
C) $85.70
D) $34.30

E) C) and D)
F) B) and D)

Correct Answer

verifed

verified

Which of the following statements about re-engineering is/are true? i.Re-engineering is the complete redesign of a process in an attempt to find new creative ways to accomplish objectivity ii.Re-engineering involves more of a 'giant leap' then the concept of activity-based management. iii.Re-engineering may entail high risks.


A) i and ii
B) i and iii
C) ii and iii
D) All of the given answers

E) All of the above
F) None of the above

Correct Answer

verifed

verified

Which of the following statements is/are true in relation to activity-based management (ABM) ? i.ABM is primarily concerned with customer value ii.Activity-based costing is the primary source of data for ABM. iii.ABM is primarily concerned with the control of inputs.


A) i and ii
B) i and iii
C) ii and iii
D) All of the given answers

E) C) and D)
F) A) and C)

Correct Answer

verifed

verified

A

Which of the following statements is/are false?


A) Cost of quality reports analyse quality costs as a percentage of total sales.
B) An increase in quality costs indicates deterioration in quality performance.
C) There can be interactions between the quality costs.
D) The traditional view of quality costs is that total quality costs can be minimised by driving the defect rate down to the acceptable quality level.

E) A) and C)
F) C) and D)

Correct Answer

verifed

verified

From a customer perspective,a value-added cost is one which:


A) increases the value of the product to the customer
B) the firm has determined is essential in the production of the product
C) on which the firm must focus
D) increases the value of the product to the customer,and the customer is prepared to pay for the added value

E) All of the above
F) A) and B)

Correct Answer

verifed

verified

Which of the following activities are non-value-added activities? i.Inspect work in process ii.Process sales orders iii.Repair drilling machine iv.Move raw material to the work station


A) i,iii and iv
B) i,ii and iv
C) i,ii and iii
D) ii,iii and iv

E) A) and B)
F) A) and C)

Correct Answer

verifed

verified

If a company has quality accreditation ,the company is then known to practice total quality management.

A) True
B) False

Correct Answer

verifed

verified

False

Which of the following are contemporary approaches to managing costs?


A) Life cycle costing
B) Target costing
C) Both life cycle costing and target costing
D) Neither life cycle costing nor target costing

E) All of the above
F) A) and D)

Correct Answer

verifed

verified

Lazy Linda Kitchen Appliances manufacturers small kitchen appliances like toasters and blenders.Last month Lazy Linda recorded the following quality costs: Lazy Linda's total internal failure cost was: Lazy Linda Kitchen Appliances manufacturers small kitchen appliances like toasters and blenders.Last month Lazy Linda recorded the following quality costs: Lazy Linda's total internal failure cost was:   A)  $9500 B)  $7500 C)  $5000 D)  $2000


A) $9500
B) $7500
C) $5000
D) $2000

E) A) and B)
F) All of the above

Correct Answer

verifed

verified

Three processes are involved in the manufacturing of Product X.First,the components go through the Machining Process,then the Assembling Process,and finally the Packaging Process.The hourly production capacity of the three processes is 500 units,600 units and 800 units respectively.How many units of Product X can be produced in one hour?


A) 500 units
B) 600 units
C) 800 units
D) 633 units

E) A) and D)
F) None of the above

Correct Answer

verifed

verified

The following four tasks take place in the concept known as target costing.i.Value engineering Ii) Establish a target price Iii) Establish a target cost Iv) Establish a target profit Which of the following correctly depicts the sequence of these tasks?


A) iii,i,iv and ii
B) ii,iv,iii and i
C) ii,iii,i and iv
D) iii,ii,i and iv

E) C) and D)
F) A) and B)

Correct Answer

verifed

verified

Orwell is about to introduce a new product and has established a target cost of $144 and a target margin on sales of 40 per cent.What is the target price?


A) $200
B) $225
C) $240
D) $280

E) A) and B)
F) A) and D)

Correct Answer

verifed

verified

Showing 1 - 20 of 78

Related Exams

Show Answer